230 kV TL

Mae Moh 4 – Phayao and Setionalizing of
230 kV Tak 2 – Nakhon Sawan Transmission Line
to Salokbat Subsation

Name of Client

EGAT

Job Description

130 km. in length, 457 towers

Type of Work Performed
and Year of Completion

Main Contractor for all construction work, 2020

Year

2016

Location

Mae Moh 4 – Phayao and Setionalizing of 230 kV Tak 2 – Nakhon Sawan Transmission Line to Salokbat Subsation

Projects

Project for reference